roadsHigh priorityopen

Road program progress across the parish

DeSoto Parish

Summary

The parish must get its HB-2 capital outlay money spent or under contract by June to qualify for more state road money. Funds are being shifted from Bethlehem Road, which is stuck on right-of-way fights, to Linwood and White Springs Roads; Bethlehem isn't being dropped, but residents there will wait longer.

At a glance

Total mentions
8
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 21, 2026.

Impact analysis

💰Financial impact

Roughly $1.5-1.6 million is at stake on Bethlehem Road, and asphalt prices have jumped from about $165 to $200 a ton installed.

✅Who benefits

Drivers on Linwood and White Springs Roads see work sooner, and the parish keeps its shot at future state funding.

⚠️Who could be affected

Bethlehem Road residents facing heavy truck traffic will wait longer for repairs.

Mentions & discussions (8)

MeetingSep 21, 2026

Regular Meeting — 2026-09-21

The administrator reported bids opening on Brown Road, construction underway on Park, Nash and other roads, and a three-year overlay plan headed to the budget process.

MeetingJun 15, 2026approved

Regular Meeting — 2026-06-15

The parish has been doing maintenance on state highways for roughly 50 years, but legally those roads belong to the state. The new formal policy ends that practice, and jurors clashed over whether state-highway residents who pay parish road taxes are being left out. Residents can now use a new parish website portal to reach DOTD directly.

MeetingMay 18, 2026

Regular Meeting — 2026-05-18

The administrator reported a long list of road and capital work: Park Road bridge project underway at $5.09 million, Brown and Nash Road projects starting, Lynwood and White Springs designs out for bid, courthouse annex and covered arena moving, plus airport taxi lane/hangar bids opening June 2.

MeetingApr 20, 2026

Regular Meeting — 2026-04-20

Cook Creek is done; Park Road, Nash Road, the Bird Streets LCDBG project and WPA Road all kick off or wrap by mid-May. The Stonewall compactor site construction has begun, targeting November completion with a new US 171 turn lane.

MeetingApr 6, 2026

Special Meeting — 2026-04-06

The parish must get its HB-2 capital outlay money spent or under contract by June to qualify for more state road money. Funds are being shifted from Bethlehem Road, which is stuck on right-of-way fights, to Linwood and White Springs Roads; Bethlehem isn't being dropped, but residents there will wait longer.

MeetingMar 16, 2026

Regular Meeting — 2026-03-16

Nash Road bids open March 17, and design work is moving on Linwood, White Springs, and Red Bluff roads with spring advertisement expected.

MeetingFeb 18, 2026

Regular Meeting — 2026-02-18

Big road projects are moving: Park Road/I-49 bids came in $580,000 under estimate, Bird Street bids came in $473,000 under, and Nash Road bids open March 17.

MeetingJan 20, 2026

Regular Meeting — 2026-01-20

Norton laid out a full slate: Brown Road bidding in March, Park Road/I-49 ($5.6M estimate backed by a $2M EDA grant) with bids due February 3, Marshall Road overlay underway, plus the Stonewall compactor site, annex HVAC and Bird Street projects all in the bid process. Several projects hit the ground this spring.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for DeSoto Parish

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.